
PDF Download Free of C_IBP_2205 Valid Practice Test Questions
C_IBP_2205 Test Engine files, C_IBP_2205 Dumps PDF
NEW QUESTION 37
Using the import/export functionality means working with groups of items that are organized into collections.What is the best practice for managing collections?
- A. You should delete collections after they have been transported.
- B. A planning area with its time profile must be bundled in one collection.
- C. A planning area with the copy operators assigned must be bundled in one collection.
- D. Configuration items should be bundled in the collections based on the SAP IBP project stream.
Answer: B,C
NEW QUESTION 38
Which of the following are capabilities of the Manage Forecast Error Calculations - Inventory Optimization app?Note: There are 2 correct answers to this question.
- A. Identifiy intermittent demand for Forecast Error CV calculations
- B. Adjust Safety Stock Recommendations based on forecast error CV input
- C. Propagate forecast error to upstream locations in a supply chain network
- D. Adjust for forecast bias in Forecast Error CV calculations
Answer: B,D
NEW QUESTION 39
You are evaluating criteria for choosing the solver to support planning for a complex supply chain. What are some of the points that should be reviewed?Note: There are 2 correct answers to this question.
- A. Push and Pull production models are used by the optimizer.
- B. Finite heuristics can achieve demand prioritization and pegging.
- C. Planning results can be generated faster by the optimizer.
- D. Prioritization of demand elements one by one is achieved by unconstrained heuristics.
Answer: A,B
NEW QUESTION 40
You are adding a value-based filter to a planning view. Which of the following conditions apply? Note:
There are 3 correct Answers to this question.
- A. You can only apply one value-based filter per planning view.
- B. These filters are always applied based on the values stored in the database.
- C. These filters can be used together with attribute totals in the same planning view.
- D. The alerts dashboard is not available if a value-based filter is set for the open planning view.
- E. You can add (or delete) planning objects to a planning view after these filters are applied.
Answer: A,B,D
NEW QUESTION 41
What function would you use to configure a year-to-date calculation?
- A. Cumulative Aggregation
- B. Dynamic Rolling Aggregation
- C. Last Period Aggregation
- D. Rolling Aggregation
Answer: A
NEW QUESTION 42
Which of the following are valid use cases for using the Realignment App?Note: There are 2 correct answers to this question.
- A. Using the realignment run to identify obsolete data
- B. Merging two locations into a new location
- C. Removing outliers from the sales history of a reference product before transferring its sales to a new product
- D. Changing customer sources and reassigning customers to new DCs
Answer: B,D
NEW QUESTION 43
Which library is used by the forecasting engine for the demand sensing algorithm?
- A. Supply chain algorithm library
- B. Predictive analytics library
- C. Demand library
- D. Heuristics library
Answer: A
NEW QUESTION 44
You are configuring disaggregation for the KF1 key figure in the Planning Areas Model Configuration app.Which methods can you use?Note: There are 3 correct answers to this question.
- A. Disaggregation according to a user-defined expression
- B. Disaggregation in batch triggered by an application job
- C. Proportional disaggregation by using KF2 in the expression
- D. Disaggregation according to a helper key figure
- E. Disaggregation according to an equal split
Answer: A,C,E
NEW QUESTION 45
Safety Stock outputs from Multistage Inventory Optimization are sent to which of these processes? Note:
There are 2 correct answers to this question.
- A. Demand Sensing with Gradient Boosting (Full)
- B. Decoupling Points determination in SAP IBP for demand-driven replenishment
- C. Charts creation in SAP Supply Chain Control Tower
- D. Supply Heuristics in SAP IBP for sales and operations
Answer: A,D
NEW QUESTION 46
You are evaluating criteria for choosing the solver to support planning for a complex supply chain. What are some of the points that should be reviewed? Note: There are 2 correct Answers to this question.
- A. Push and Pull production models are used by the optimizer.
- B. Finite heuristics can achieve demand prioritization and pegging.
- C. Planning results can be generated faster by the optimizer.
- D. Prioritization of demand elements one by one is achieved by heuristics.
Answer: A,B
NEW QUESTION 47
What is a prerequisite for modeling outsourced manufacturers with production capacity?
- A. Model target inventory and stocks at the outsourced location.
- B. Use production lead times and offsets to manage components at the outsourced location.
- C. Ensure that multiple modes of transportation are set up.
- D. Model production costs for internal and external production resources to model priority.
Answer: D
NEW QUESTION 48
What do you need to be aware of when using multiple pairs of key figures in one copy operator? Note: There are 2 correct answers to this question.
- A. If necessary target key figures values are disaggregated.
- B. Copying multiple key figures can be processed sequentially.
- C. If necessary source key figures values are disaggregated.
- D. Copying multiple key figures on different planning levels is not possible.
Answer: B,C
NEW QUESTION 49
You are setting up planing with lot sizes.What are some of the properties of lot sizes that you need to be aware of?Note: There are 2 correct answers to this question.
- A. Periodic lot size setting overrides the minimum lot size.
- B. Lot sizes are time-independent master data settings.
- C. Lot sizes are applicable for production and handling quantities.
- D. Lot sizes are applicable for production and transportation quantities.
Answer: B,C
NEW QUESTION 50
Which conditions have to be fulfilled as a prerequisite to maintain a key figure disaggregation?Note: There are
2 correct answers to this question.
- A. The key figure is stored and all editable.
- B. The key figure is calculated and system editable.
- C. The key figure is calculated and all editable.
- D. The key figure is stored and system editable.
Answer: A
NEW QUESTION 51
Which of the following approaches could you take to reduce run times of an optimizer? Note: There are
2 correct Answers to this question.
- A. Avoid using telescopic time buckets.
- B. Use a subnetwork ID to reduce the size of the problem.
- C. Increase the use of incremental lot size beyond the frozen horizon.
- D. Split into multiple planning areas to support weekly vs. daily planning needs.
Answer: A,B
NEW QUESTION 52
Which supply chain challenge is addressed by SAP IBP for demand?
- A. Inability to synchronize supply and demand
- B. Inability to respond to short-term changes in supply and demand
- C. Inability to arrive at consensus demand
- D. Inability to understand and shape actual demand
Answer: D
NEW QUESTION 53
What are S&OP operator (optimizer) parameters associated with demand fair share?
- A. Number of fair share segments. Additional tiering costs (default). Number of fair share segments late delivery
- B. You want to copy a custom planning area that was built during the SAP IBP implementation to model a separate process.
- C. Number of fair share segments. Additional tiering costs (default). Target inventory violation cost
- D. Number of fair share segments. Maximum inventory. Additional tiering costs (default)
- E. Number of fair share segments. Maximum days of coverage. Number of fair share segments late delivery
Answer: A
NEW QUESTION 54
......
Pass Your SAP Certified Application Associate C_IBP_2205 Exam on Apr 18, 2023 with 80 Questions: https://exams4sure.pass4sures.top/SAP-Certified-Application-Associate/C_IBP_2205-testking-braindumps.html